Promised date vs planned date: why you need both

The date on the purchase order is a promise to the customer. The date your planner works to is a plan. Keeping them in one column hides the slip until the customer calls. Here is how to keep both, and what each one is for.

By Pratik ManeProduct

6 min read

Ask three people in a small factory when an order is due and you may get three different dates. Sales quotes the date on the customer's purchase order. Planning has a date in mind based on what is in the shop. The production supervisor has a date based on what actually happened this week. Each of them is right about something.

The trouble starts when a single "dispatch date" column has to hold all three. Somebody overwrites it, and the information that mattered most, how far the plan has drifted from the promise, disappears.

The fix is simple and costs nothing: keep two dates, and give each a clear job.

The promised date: what you told the customer

The promised date (we call it the PO dispatch date) is the date written on the purchase order, or the date you agreed in writing when you accepted it. It is a commitment to someone outside your company.

It should change rarely, and only when the customer agrees to a new date. If a customer emails to say their site will not be ready until March, that is a reason to change it. A late casting from your foundry is not.

Treat it like the terms on the PO: it records what was agreed, not what you hope will happen.

The planned date: what you are working towards

The planned date (we call it the tentative dispatch date) is your team's honest, current estimate of when the order will leave. It is internal. It moves when reality moves: a vendor is late, a design change comes in, the customer has not released the advance.

This is the date your planner, purchase team and shop floor should work to. It is the date that tells you what is due this week, what is overdue and what you can realistically promise to the next customer.

If the planned date never changes, it is probably not being looked at.

Why one column is not enough

Here is a typical sequence with one date column:

  1. A customer in Pune orders a machine. The PO says dispatch by 30 June. The sheet says 30 June.
  2. In May the gearbox vendor slips by three weeks. Planning changes the cell to 21 July.
  3. In June the customer calls to ask whether everything is on track for 30 June.

Nobody in the meeting can see from the sheet that the order was ever due on 30 June. The original promise is gone. The person who took the call has to search old emails to work out what was agreed, and the customer hears about the delay from the customer's side first.

With two dates, the same sequence looks very different. The PO date stays at 30 June. The planned date moves to 21 July. The difference, three weeks late against the promise, is visible to everyone from the moment it happens, not from the moment the customer calls.

Order Promised (PO) Planned Slip
Machine for a Pune customer 30-Jun 21-Jul +21 days
Spares for a Nashik customer 15-Jun 12-Jun none
Panel for a Chennai project 05-Jul (not planned yet) unknown

The third row matters too. An order with a promise but no plan is a risk nobody has looked at yet.

What each date is good for

Once the two are separate, each answers a different question.

The planned date tells you what to do this week. Sort open orders by planned date and you have a working list: what is overdue, what is due in the next seven days, what is coming in the next month. This is the list for the morning meeting.

The promised date tells you who to call. Any order whose planned date is now later than its promised date needs a conversation with the customer, before they ask. The earlier you call, the more options both sides have.

The gap between them tells you how good your promises are. If most orders slip by two to four weeks against the PO, the problem is not in production. It is in how dates are quoted. That is a conversation for sales and planning together, with the evidence in front of them.

Penalty risk needs both. If some customers can deduct a penalty for late delivery, the orders to watch are those for such customers where the plan is already later than the promise, or where the planned date has already passed. You cannot see that from one date.

Rules that keep the two dates honest

A few habits make this work in practice:

  • Set the promised date once, from the PO. Change it only with the customer's written agreement, and note where that agreement is.
  • Plan every order. An order without a planned date is invisible in every list that sorts by date. Make "missing planned date" something you check weekly.
  • Never change a planned date silently. Each change should record the old date, the new date and a short reason. Over a few months those reasons show you where delays really come from. (We wrote about this in Delay reasons: the cheapest way to stop orders slipping.)
  • Review the slips, not just the overdue list. "Overdue" only shows orders whose planned date has passed. Orders that are on plan but weeks behind the promise need attention too.

A useful test: pick any open order and ask, "What did we promise, what do we expect now, and why are they different?" If the answer takes more than ten seconds to find, the dates are not doing their job yet.

Doing this in a spreadsheet

You do not need new software to start. In your current order sheet:

  1. Rename your dispatch date column to "PO dispatch date" and stop editing it except for agreed changes.
  2. Add a "Planned dispatch date" column and fill it for every open order.
  3. Add a "Slip (days)" column: planned date minus PO date.
  4. Add "Previous planned date" and "Reason for change" columns, and fill them every time the planned date moves.
  5. Format both date columns as real dates, so that sorting works.

This takes an afternoon. The harder part is the discipline of using it, especially step 4, because a spreadsheet will not stop anyone from overwriting a cell.

How Kramaline handles it

In Kramaline every order has both dates from the start. The order summary sorts by the planned date, shows a due badge (days left or days late), and has a "Slip vs PO" column. Changing the planned date after it is first set asks for a delay reason and keeps every earlier date in the order's history. The dashboard compares promise and plan across all open orders, and flags orders that could attract a late-delivery penalty.

Whether you use a tool or a sheet, the idea is the same: keep the promise and the plan apart, and look at the gap every week. It is the cheapest early warning a small manufacturer can have.