Delay reasons: the cheapest way to stop orders slipping

Every time a planned dispatch date moves, write down why. A short, fixed list of reasons turns months of "it got delayed" into a clear picture of where your orders really get stuck, and what to fix first.

By Omkar DebadwarStrategy

5 min read

Most small manufacturers know which orders are late. Far fewer know why orders are late, in general, across the year. Ask in a review meeting and you will hear confident answers: "It is always the vendors", "Customers keep changing the specs", "We are short of welders". Some of these will be true. Some will be what was true two years ago.

There is a simple habit that replaces opinion with evidence, and it costs almost nothing: every time a planned dispatch date moves, record the reason from a short, fixed list.

Why "delayed" is not enough

When a date moves in a shared sheet, the usual record is the new date and nothing else. Sometimes there is a remark: "vendor", "cust", "pending from design", "see mail". These notes are better than nothing, but they cannot be counted. You cannot sort a column of free text and learn that a third of your delays last quarter came from one cause.

The result is that every delay is handled as a one-off. The planner chases the vendor for this order, the order eventually leaves, and the same thing happens next month with a different order.

A short list beats a long one

The list of reasons should be short enough that people choose quickly and honestly. Six to eight reasons is usually right. A typical list for a small machine builder or fabricator might be:

  • Technical specification or work order not finalised
  • Procurement or cash flow
  • Custom design work
  • Customer site or infrastructure not ready
  • Customer request
  • Vendor or outsourcing delay
  • Other

A few principles help:

  • Cover the big buckets, not every case. "Vendor delay" is more useful than separate reasons for each vendor. The vendor's name can go in a note.
  • Separate what is ours from what is the customer's. "Customer site not ready" and "customer request" are different from "procurement". They lead to different conversations, and possibly different penalties.
  • Keep "Other" but watch it. If "Other" becomes the most common reason, the list is missing something. Add the missing reason and move on.
  • Do not change the list every month. Reasons are only useful if they mean the same thing over time.

Make the reason mandatory, but only when it matters

The first planned date of an order needs no reason; it is simply the plan. Every change after that should need one. If the reason is optional, it will be skipped exactly when people are busiest, which is exactly when delays happen.

It also helps to record the reason at the moment the date changes, by the person who changes it. Reconstructing reasons at month end from memory gives you the story people remember, not what happened.

Tip: add a one-line note next to the reason when it helps, such as "gearbox from vendor B, promised 12-Aug". The reason is for counting; the note is for the person who picks up the order tomorrow.

What the reasons tell you after three months

Once reasons are recorded consistently, a simple count by reason shows where orders get stuck. You can count in two ways, and both are useful:

Count by Answers
Number of date changes Which causes come up most often
Total days added Which causes cost the most time

The two lists are often different. Customer requests may cause many small moves of a few days each. Specification problems may happen less often but add weeks each time. The second kind is usually where to start.

Some patterns that commonly show up:

"Specification not finalised" near the top. Orders are being released to production before the technical details are agreed. The fix is upstream: a short checklist that must be complete before an order gets a planned date, and a clear owner for chasing the customer.

"Procurement or cash flow" near the top. Long-lead items are ordered too late, or advances arrive late. Look at when purchase orders go out relative to order acceptance, and whether advance terms are being followed up.

"Vendor delay" concentrated on a few vendors. This gives you a fair, factual basis for a conversation with those vendors, or for finding a second source.

"Customer site not ready" growing. Machines are being finished before customers can receive them. This affects your cash and your floor space. It may be worth asking for site readiness confirmation before final assembly, or agreeing storage charges.

None of these conclusions needs a consultant. They need three months of honest reasons.

Common objections

"People will just pick any reason." Some will, at first. Review the reasons in the weekly meeting for the orders that moved that week. When people see the reasons being read, they get more careful.

"It takes too long." Choosing from a list of seven takes a few seconds. Explaining an unexplained delay to a customer takes much longer.

"Our delays are too complicated for a list." Most delays have one main cause. Pick the main one and use the note for the rest. Perfect classification is not the goal; a usable pattern is.

Starting in a spreadsheet

In a shared order sheet you can do this today:

  1. Agree the list of reasons in your next review meeting and write it on a separate tab.
  2. Add a "Reason for change" column next to your planned date, with data validation that only allows values from that list.
  3. Add a "Previous planned date" column, so that you can measure the days added.
  4. Every Friday, filter for orders whose planned date changed that week and read the reasons aloud.

The weak point is step 3: a sheet keeps only the latest change unless someone copies the history somewhere by hand. After the second or third change on the same order, the earlier ones are usually lost.

How Kramaline handles it

In Kramaline the list of delay reasons is part of the company's settings, so an admin can keep it short and stable. Changing an order's tentative dispatch date after it is first set asks for a reason and an optional note, and keeps every earlier date and reason in the order's history. The dashboard has a "Why orders slip" chart that counts changes by reason, by number or by days added, for the filters you choose.

The tool matters less than the habit. Record why dates move, look at the pattern every few months, and fix the biggest cause first. It is the cheapest improvement project a small factory can run.